Cyprium Metals is getting closer to resuming trading on the Nifty, with predevelopment almost complete and financing negotiations continuing.|Trending-Topics




Cyprium Metals is getting closer to resuming trading on the Nifty, with predevelopment almost complete and financing negotiations continuing.

 Cyprium Metals, Inc.'s Predevelopment work is continuing concurrently with the financing process, and CYM) is getting closer to restarting its Nifty copper project north of Western Australia.

Cyprium noted in its most recent restart update that most of Nifty's operational readiness and environmental cleanup tasks had been completed.

Barry Cahill, the managing director of Cyprium, stated that "multiple parties" had progressed the finance process for the restart.

"We have reduced personnel throughout the organization in order to save money until we complete the financing and begin the refurbishment schedule in earnest," the business claims.""Our employees have done an excellent job of getting Cyprium to the go-line for when the finance process is finished, and the progress that has been made up to this point has been remarkable.""To support Cyprium's resumption of business, the company that owns the Nifty copper project anticipates acquiring debt financing for between $240 million and $260 million.

Working capital and a cost overrun contingency are included in the package.

The company will provide the market with updates as negotiations progress regarding the funding. All parties have had "positive" discussions.

In March of this year, a study on restarting operations at Nifty was released.

The project's annual production of copper cathode, which includes oxide open pit mining and retreating heap leach material, is the company's goal.

Nifty already contains 25.9 million tonnes of mined and stacked ore, including heap leach material, containing 0.65 percent copper.

Copper recovery rates can be as high as 85% with retreating heap leach material and 90% with processing oxide ore.

Additionally, Nifty has a substantial amount of existing infrastructure, including a 21MW gas turbine power station, a 2.8Mtpa sulfide concentrator, a 25,000tpa copper cathode heap leach extraction-electrowinning facility, pipeline, and power distribution systems.

Water supply and reticulation systems, a mining village, complete heavy vehicle workshops, inventory, a sealed all-weather airstrip, and network and communications capabilities are additional essential infrastructure.

In May, the project's resource update included 940,200 t of contained copper metal.

The company thinks that the previous heap leach pads contain an additional 91,000 t of contained copper.

Comments